Engineering services provided by: Lockwood, Andrews & Newnam, Inc.
Authorized Budget: $9,800,000.00
Project Phases of Development:
Preliminary Engineering - 100% Complete
Utility Engineering - 40% Complete
Environmental - 100% Complete
ROW Acquisition - 90% Complete
Design - 98% Complete
Begin Construction (Tentative Per Council Approval) - February 2016
Goforth Rd. Highlights
- Facilitate the movement of traffic at Fuentes Elementary School
- Placement of 3-way stop condition at Goforth, 4-way stop at Brent Blvd.
- Bridge constructed at Plum Creek crossing improving drainage system
- Lane widths designed to calm traffic velocity
Status Updates
Approved Oct 8, 2014: Supplement No. 1 to Lockwood, Andrews, and Newnam, Inc., San Antonio, Texas, in an amount not to exceed $102,863.00 for the purpose of providing Right-of-Way services and documents, (parcel plats, appraisal reports, etc.); and an archeological survey necessary for the acquisition of properties for the Goforth Road proposed roadway improvements.
Approved Nov 5, 2014: Supplement No. 2 to Lockwood, Andrews, and Newnam, Inc., San Antonio, Texas, in an amount not to exceed $204,930.25 for the purpose of providing engineering services and documents necessary for the development of project plans, estimates, specifications for bidding of Goforth extension new location roadway improvements.
Goforth Extension: Roadway plans are approximately 95% complete. Right of Way has not been acquired for the extension.
Approved July 7, 2015: Supplement No. 3 to Lockwood, Andrews, and Newnam, Inc., San Antonio, Texas, in an amount not to exceed $75,198.00 for the purpose of providing utility engineering coordination, validating reimbursable utility owner fees and improvements, additional easement instruments and documents necessary for the relocation of utilities.