This is the current construction report for the new Kyle Public Library. Construction continues at an excellent pace. The latest photos show that parts of the interior are being painted. Please note the following:

A. Work Performed This Week:

  •  Window installation completed
  •  Tape and bed completed
  •  Security & data rough-in continued
  •  Masonry continued – punch and clean-up
  •  Started HVAC trim
  •  Paint continued
  •  Site fine grading completed
  •  HVAC start-up
  •  Ceiling grid continued

B.  Work Scheduled For The Next Two Weeks:

  •  Plaza trellis work
  •  Start restroom accessories