This is the current construction report for the new Kyle Public Library. Please feel free to view the slide show of the latest and greatest pictures of the new library. Also, the complete construction report can be accessed by selecting the link under "Supporting Documents." Please note the following:
A. Work Performed This Week:
Completed building trim
Continued security and data rough-in
Continued masonry (punch and clean up)
Continued painting
Continued installing ceiling grid
Continued working on Plaza trellis
Removed temporary power
Completed cabinets
Continued irrigation and top soil
Installed restroom accessories
Completed above grid final inspections
Began installing interior doors
B. Work Scheduled For The Next Two Weeks:
Complete canopies
Start site concrete in Plaza
C. Pending Items Needed from Owner:
None at this time
D. Long Lead Time Items:
None at this time
E. Other Items or Concerns:
None at this time