City of Kyle Downtown Streetscape Project Updates

Project Timeline and Calendar

(All times & dates are approximate and subject to change)

Updated December 28th, 2007

Begin Date
Scope
Duration
Status
Phase 1 April 14

Front Street between Train Depot and City Hall.

NO PARKING ON N. FRONT ST. THIS PHASE

6.5 Weeks Completed
Phase 2.1 June 10

All utility and paving work involving the middle of Center Street.

NO PARKING ON CENTER ST. DURING THIS PHASE

Six Weeks

Completed

Phase 2.2 July 17

All utility, paving and concrete work involving the South side of Center Street.

NO PARKING ON CENTER ST. DURING THIS PHASE

Six Weeks

Completed

Phase 2.3 October 15

All utility, paving and concrete work involving the North side of Center Street.

Parking is now available on the south side of Center Street.

 

Five Weeks

Complete

Phase 2.4 October 15

All utility, paving and concrete work involving the East and West ends of Center Street.

LIMITED PARKING ON CENTER ST. DURING THIS PHASE

 

Three Weeks

Work on the West end of Center Street is completed

Work on the Eastern end will be completed by Dec 28th.

Phase 2.5 December 10

Asphalt paving of North half.

LIMITED PARKING ON CENTER ST. DURING THIS PHASE


One Week Complete
Phase 2.6 December 14

Asphalt paving of South half.

LIMITED PARKING ON CENTER ST. DURING THIS PHASE

Striping of Center Street will occur on Saturday, December 29th.

One Week Complete


  If weather holds out and if suppliers meet the schedule, the project should be completed by December 31. Trees, benches and trashcans are scheduled to be installed on or before January 15th.

 

Expected Project Completion - December 31st, 2007