4.16.07 Traffic detouring equipment arrives |
5.4.07 Underground drainage pipes delivered |
|
|
5.23.07 Removal of old asphalt surface |
5.23.07 Curbing near completion. Sidewalk being readied. |
|
|
5.25.07 Colored concrete poured |
5.25.07 Stamped to look like pavers and bricks |
|
|
7/2/07 Colored concrete is poured in center crosswalks |
7/2/07 Before concrete sets, templates are pounded on |
|
|
7/2/07 Stamped colored concrete is better than pavers |
7/2/07 Different templates create different brick patterns |
|
|
7/2/07 End result looks like brick pavers |
7/2/07 Center portion of Center Street with crosswalks |
|
|
8/1/07 Old Sidewalk removed on south side of Center St |
8/1/07 Framing for new sidewalk taking shape |
|
|
8/7/07 Giant Rock Saw quickens the trenching job |
8/7/07 Demo of sidewalk continues on Center St |
|
|
9/17/07 Traffic Signal Pole foundation frame set |
9/17/07 Underground storm pipes are laid |
|
|
10/2/07 Burleson St crosswalk gets poured |
11/6/07 TxDOT drills for traffic signal pole on north side |
|
|
11/6/07 South side is complete |
12/11/07 Final section on Center St crosswalk is poured |
|
|
12/17/07 Concrete is pouring freely as end in sight |
12/27/07 Resurvacing of Center Street gets started |