City Park Improvements
Project Type:
Parks
Project Status:
Ongoing
Date Received:
Friday, January 6, 2023
For more information about Parks Improvements Projects, contact the Parks and Recreation Office at 512-262-3939 or parks@cityofkyle.com.
Project Name/Location | Details | Status | Estimated Completion |
Lake Kyle Park | New Signage | In progress | September 2023 |
Park Cameras | Complete | Complete as of March 2024 | |
Horseshoe Pit Removal | In progress | September 2023 | |
New Restrooms | The building pad has been excavated and the base installed. Utility trenches have been excavated. Plumbing and electrical piping set is scheduled for this week. Building will be delivered next week. | October 2024 | |
Inclusive Playground | Groundwork began. | Fall 2023 | |
BBQ Pit Improvements | In progress | September 2023 | |
Dam Repair | When the lake fills back up, fishing can resume at Lake Kyle. Irrigation and seeding to begin. | Aug-23 | |
Steeplechase Park | Repainting Basketball Court | Complete | Complete as of October 2023 |
Park Cameras | Complete | Complete as of March 2024 | |
Splashpad | Installation is complete. Staff in training. |
Open to the public in May 2024 |
|
Disc Golf Course Improvements | In planning | Fall 2024 | |
New Restrooms | Building has been set. Interior utilities need to be connected. Next is final site grading and final inspection. |
Summer 2024 | |
Ball Field Improvements | In progress | TBD | |
New Signage | In progress | Summer 2024 | |
New Swings | In progress | Summer 2024 | |
Volley Ball Court Improvements | In progress | Summer 2024 | |
Irrigation Around Dog Park | In progress | Summer 2024 | |
BBQ Pit Repairs | In progress | Summer 2024 | |
New Trash Cans | In progress | Summer 2024 | |
Gregg‐Clarke Park | Irrigation to Ball Fields and soccer field | Complete | Complete as of December 2022 |
New Scoreboard and Flooring in Ash Pavilion | Complete | Complete as of May 2023 | |
Park Cameras | Complete | Complete as of March 2024 | |
New Restrooms | Building has been set and utilities are connected. Final utility inspection is next. |
October 2024 | |
Ball Field Improvements | RFP to be reposted. | TBD | |
Skate Park | At 60% Design | Construction to begin in the Summer of 2024 | |
Splashpad | Installation is complete. Staff in training. |
Open to the public in May 2024 |
|
Waterleaf Park | New Signage | In progress | September 2023 |
Park Cameras | Complete | Complete as of March 2024 | |
New Restrooms | The building pad has been excavated. | October 2024 | |
Ball Field Improvements | In progress | September 2023 | |
Playground Improvements | In progress | September 2023 | |
Plum Creek Trail | Interpretive Signage | In progress | September 2023 |
Benches | In progress | September 2023 | |
Trash Cans | In progress | September 2023 | |
Masonwood Park | Greenbelt with fitness equipment | In progress RFP now to post in August. | 2023 |
Lineberger Lake Park | Fishing Dock | In planning | TBD |
Covered Picnic Area | In planning | TBD | |
Aeration | In progress | TBD | |
Cool Springs Park | Aeration | Complete | Complete as of March 2024 |
Mary Kyle Hartson Park | New Restrooms | The building pad has been excavated. Utility points have been identified. City Departments are coordinating and addressing Miller Street and Main Street plumbing and electrical before proceeding. |
October 2024 |
Park Cameras | Complete | Complete as of March 2024 | |
Kyle Regional Sportsplex | Tournament Size Sports Fields | In progress | TBD |
Picnic Areas | In progress | TBD | |
Pavilion | In progress | TBD | |
Playground | In progress | TBD | |
Sand Volleyball Courts | In progress | TBD | |
Heroes Memorial Park | Plaque Repairs | In Progress | September 2023 |
Park Cameras | No cameras have been installed yet. Awaiting internet. | March 2024 | |
Pond Algae Treatment | In Process | Ongoing | |
La Verde Park | Park Cameras | Cameras have been installed yet. Awaiting internet. | March 2024 |