Bunton Creek Interceptor Ph 2

Project Type:
Road / Sidewalk
Project Status: 
In Construction

This project is to construct the remaining section (red dashed line on location map) of the Bunton Creek Interceptor.

The contractor is Smith Construction. 

Other than construction entrances along the route, we don’t anticipate any lane/road closures.

Bunton Creek Village Lift Station to City of Kyle Wastewater Treatment Plant
Preconstruction meeting held on Nov 12, 2020
250 calendar day contract
Start Work Date: December 7, 2020

 

Bunton Creek Interceptor location map
Bunton Creek Update
Bunton Creek Update
Bunton Creek Update
Status Updates

As of 9/6/22:

Based on pay estimates, project is 94% complete

Southlake Lift Station

Electrical work remains to be done - PW coordinating with PEC

Bunton Creek Lift Station

Electrical work remains to be done - PW coordinating with PEC