Bunton Creek Interceptor Ph 2
Project Type:
Road / Sidewalk
Project Status:
In Construction
This project is to construct the remaining section (red dashed line on location map) of the Bunton Creek Interceptor.
The contractor is Smith Construction.
Other than construction entrances along the route, we don’t anticipate any lane/road closures.
Bunton Creek Village Lift Station to City of Kyle Wastewater Treatment Plant
Preconstruction meeting held on Nov 12, 2020
250 calendar day contract
Start Work Date: December 7, 2020
Status Updates
As of 9/6/22:
•Based on pay estimates, project is 94% complete
Southlake Lift Station
•Electrical work remains to be done - PW coordinating with PEC
Bunton Creek Lift Station
•Electrical work remains to be done - PW coordinating with PEC