6 Creeks Wastewater Improvements Project

Project Type:
Utility
Project Status: 
In Construction
Date Received: 
Monday, March 18, 2024

There will be road closures on Old Stagecoach Road done in 2 phases for the 6 Creeks Wastewater Improvements Project:

  • Phase 1: From Monday, March 25 - Friday, June 14, Old Stagecoach Road from Center Street (FM 150) to just North of Cypress Forest Drive will be closed. Drivers wanting to access Cypress Forest Drive will be detoured to either take Center Street, to Cypress Road, to Arapaho Drive, to Cypress Forest Drive or to take Veterans Drive, to Old Stagecoach Road, to Cypress Forest Drive.
  • Phase 2: After phase 1 is complete, Old Stagecoach Road from just North of Cypress Forest Drive to Three Forks Drive will be closed.

Work hours will be Monday through Saturday from 6:30 a.m. to 6 p.m. All Construction is weather permitting. Drivers are asked to obey traffic warning signs, detours and watch out for heavy equipment and flaggers

6 Creeks Delay
Status Updates

April 26, 2024:

Due weather and utility issues, Phase 1 of the 6 Creeks Wastewater Improvements Project on Old Stagecoach Road from Center Street (FM 150) to just North of Cypress Forest Drive has been delayed. Phase 1 is now set to be completed and reopened on Friday, June 14, weather permitting. 

Drivers wanting to access Cypress Forest Drive will be detoured to either take Center Street, to Cypress Road, to Arapaho Drive, to Cypress Forest Drive or to take Veterans Drive, to Old Stagecoach Road, to Cypress Forest Drive.

Work hours will be Monday through Saturday from 6:30 a.m. to 6 p.m. All Construction is weather permitting. 

Drivers are asked to obey traffic warning signs, detours and watch out for heavy equipment and flaggers. Phase  2 of the project, which will close Old Stagecoach Road from just North of Cypress Forest Drive to Three Forks Drive, will start after Phase 1 is complete.

March 18, 2024:

Old Stagecoach Road will be closed from Center Street to the north of Cypress Forest Drive for the 6 Creeks Wastewater Improvements Project from Monday, March 25 - Monday, April 29.

Drivers wanting to access Cypress Forest Drive will be detoured to either take Center Street, to Cypress Road, to Arapaho Drive, to Cypress Forest Drive or to take Veterans Drive, to Old Stagecoach Road, to Cypress Forest Drive.

Work hours are Monday through Saturday from 6:30 a.m. to 6 p.m. All Construction is weather permitting. Drivers are asked to obey traffic warning signs, detours and watch out for heavy equipment and flaggers.