Southside Wastewater Improvements

Project Type:
Utility
Project Status: 
Complete
Location: 
Kyle, TX 78640

The scope of work includes approximately 16,500 linear feet of gravity mains, 9,500 linear feet of force main, 2,000 linear feet of reclaim water main, lift station, manholes, borings, and other various appurtenances.

One crew working on the Post Road lift station, second crew working on gravity and reclaimed water lines near TDCJ, third crew working on bores on north end of project.

Map of Southside wastewater improvements
Southside wastewater construction Progress
Southside wastewater construction Progress
Status Updates

As of 4/18/23:

Based on pay estimates, overall project is 93% complete 
Contractor issued final punch list
Pending Change Order submittal for purchase of air condition unit for Southside Lift Station per PW request
New Installed Infrastructure
     •12,958 LF Wastewater Interceptor
     •7,750 LF Force Main
     •1,865 LF Reuse Main
     •220 LF Water Main
     •Southside Wastewater Lift Station