Southside Wastewater Improvements
The scope of work includes approximately 16,500 linear feet of gravity mains, 9,500 linear feet of force main, 2,000 linear feet of reclaim water main, lift station, manholes, borings, and other various appurtenances.
One crew working on the Post Road lift station, second crew working on gravity and reclaimed water lines near TDCJ, third crew working on bores on north end of project.
Status Updates
As of 4/18/23:
•Based on pay estimates, overall project is 93% complete
•Contractor issued final punch list
•Pending Change Order submittal for purchase of air condition unit for Southside Lift Station per PW request
•New Installed Infrastructure
•12,958 LF Wastewater Interceptor
•7,750 LF Force Main
•1,865 LF Reuse Main
•220 LF Water Main
•Southside Wastewater Lift Station