City Park Improvements

Project Type:
Parks
Project Status: 
Ongoing
Date Received: 
Friday, January 6, 2023

 

For more information about Parks Improvements Projects, contact the Parks and Recreation Office at 512-262-3939 or parks@cityofkyle.com.

 

Project Name/Location Details Status Estimated Completion
Lake Kyle Park New Signage In progress September 2023
  Park Cameras Complete Complete as of March 2024
  Horseshoe Pit Removal In progress September 2023
  New Restrooms The building pad has been excavated and the base installed. Utility trenches have been excavated. Plumbing and electrical piping set is scheduled for this week. Building will be delivered next week. October 2024
  Inclusive Playground Groundwork began. Fall 2023
  BBQ Pit Improvements In progress September 2023
  Dam Repair When the lake fills back up, fishing can resume at Lake Kyle.  Irrigation and seeding to begin. Aug-23
Steeplechase Park Repainting Basketball Court Complete Complete as of October 2023
  Park Cameras Complete Complete as of March 2024
  Splashpad Installation is complete.
Staff in training.

Open to the public in May 2024

  Disc Golf Course Improvements In planning Fall 2024
  New Restrooms Building has been set. Interior utilities need to be
connected. Next is final site grading and final inspection.
Summer 2024
  Ball Field Improvements In progress TBD
  New Signage In progress Summer 2024
  New Swings In progress Summer 2024
  Volley Ball Court Improvements In progress Summer 2024
  Irrigation Around Dog Park In progress Summer 2024
  BBQ Pit Repairs In progress Summer 2024
  New Trash Cans In progress Summer 2024
Gregg‐Clarke Park Irrigation to Ball Fields and soccer field Complete Complete as of December 2022
  New Scoreboard and Flooring in Ash Pavilion Complete Complete as of May 2023
  Park Cameras Complete Complete as of March 2024
  New Restrooms Building has been set and utilities are
connected. Final utility inspection is next.
October 2024
  Ball Field Improvements RFP to be reposted. TBD
  Skate Park At 60% Design Construction to begin in the Summer of 2024
  Splashpad Installation is complete.
Staff in training.

Open to the public in May 2024

Waterleaf Park New Signage In progress September 2023
  Park Cameras Complete Complete as of March 2024
  New Restrooms The building pad has been excavated. October 2024
  Ball Field Improvements In progress September 2023
  Playground Improvements In progress September 2023
Plum Creek Trail Interpretive Signage In progress September 2023
  Benches In progress September 2023
  Trash Cans In progress September 2023
Masonwood Park Greenbelt with fitness equipment In progress RFP now to post in August.  2023
Lineberger Lake Park Fishing Dock In planning TBD
  Covered Picnic Area In planning TBD
  Aeration In progress TBD
Cool Springs Park Aeration Complete Complete as of March 2024
Mary Kyle Hartson Park New Restrooms The building pad has been excavated. Utility points have been identified. City Departments are coordinating and
addressing Miller Street and Main Street plumbing and electrical before
proceeding.
October 2024
  Park Cameras Complete Complete as of March 2024
Kyle Regional Sportsplex Tournament Size Sports Fields In progress TBD
  Picnic Areas In progress TBD
  Pavilion In progress TBD
  Playground In progress TBD
  Sand Volleyball Courts In progress TBD
Heroes Memorial Park Plaque Repairs In Progress September 2023
  Park Cameras No cameras have been installed yet. Awaiting internet. March 2024
  Pond Algae Treatment In Process Ongoing
La Verde Park Park Cameras Cameras have been installed yet. Awaiting internet. March 2024