Citywide Microsurfacing to begin July 18

Published:
Wednesday, July 13, 2022
<< Back to News
Citywide Microsurfacing to begin July 18

     DATE/TIME: Monday, July 18 - Tuesday, July 26 

     WEBSITE: www.cityofkyle.com/publicworks/citywide-microsurfacing-2022 

KYLE, TEXAS – Viking Construction will be microsurfacing roads to improve the appearance and life of the road beginning Monday, July 18 and going through Tuesday, July 26. 

Work hours will be Monday through Friday from 8 a.m. - 5 p.m. All vehicles along the affected stretches of road must be moved before 8 a.m. the day of the microsurfacing. Please plan accordingly. 

Microsurfaced roads will need to be closed after being treated, but will be reopened after the coating has cured, which will take a few hours. The city asks that residents do not drive or walk on the new surface until the crew has opened the street. Fresh coating can stick to car tires and paint. When the microsurfacing is “cured,” the work crew will remove the cones or barricades. 

Residents may see works crews in their neighborhoods between Monday, July 11 and Thursday, July 14 removing/grinding down pavement markings as well as patching and cleaning up street areas. 

Monday, July 18  

  • Spring Branch Cove  
  • Fall Creek Drive from Spring Branch Loop to Spring Branch Loop 
  • Keegans Way from Alexis Way to Spring Branch Loop 
  • Scott Street and W. Moore Street from Opal Lane to S. Front Street 

Tuesday, July 19  

  • Scott Street and W. Moore Street from Opal Lane to S. Front Street 
  • Verano Drive from Estival Drive to the Cul-de-sac 
  • Estival Drive from Summer Drive to Verano Drive 
  • Estival Drive Fall Drive to the Cul-de-sac 
  • Estival Drive from Summer Drive to Fall Drive  

Wednesday, July 20  

  • Rummel Drive from New Country Road to the Cul-de-sac 
  • Olson Cove from New Country Road to the Cul-de-sac 
  • Tower Drive from New Country Road to the Cul-de-sac 
  • Gina Road from New Country Road to Waterleaf Boulevard 

Thursday, July 21  

  • Fairway from Jack C Hays Trail to Hogan  

Friday, July 22  

  • Fairway from Jack C Hays Trail to Hogan 
  • New Country Road from FM 150 to Myrtle Street  

Monday, July 25  

  • Spring Branch Loop from Fall Creek Drive to Fall Creek Drive 
  • Alexis Way from Spring Branch Drive to Fall Creek Drive 

Tuesday, July 26  

  • Autumn Drive from Summer Drive to Verano Drive 
  • Summer Drive from Four Seasons Farm Boulevard to Estival Drive 
  • Spring Drive from Four Seasons Farm Boulevard to Estival Drive 
  • Kyle Crossing from Vista Ridge Drive to the I-35 Frontage Road 

This schedule could be adjusted based on weather. For more information, go to www.cityofkyle.com/publicworks/citywide-microsurfacing-2022